|
|
West Rand Mining Operation
Project Description
The West Rand Mining Operations (“WRMO”) consist of the Middelvlei Mine, which is an early stage gold
mining project, located on the Witwatersrand Basin, south of the town of Randfontein, Gauteng, South
Africa (Figure 5). Three reefs have been identified through drilling and mapping on the property, namely
the Black Reef, which has proved to be the most economically viable at present, the VCR and the MVR.
The mineral asset is one of the few remaining gold bearing orebody’s that can be mined via opencast
mining methods in the area.
The Black Reef has been mined both as a shallow underground and a surface operation by Lindum Reefs
to the north of Middelvlei Mine. From these mining activities, it was clear that payable Black Reef lies
within very well defined pay shoots, which run parallel to the regional strike of the underlying Central
Rand Group rocks (north-east to south-west). The VCR and MVR have also been mined extensively to the
south of Middelvlei, on the Gold Fields South Africa Ltd (“Gold Fields”) Venterspost property.
The project has a long history of exploration activity conducted by various organisations. Most recently,
Gold Fields conducted a large-scale drilling programme, as well as surface and underground sampling
on the property and information from these activities was used as a basis for the follow up exploration.
MGI became involved with the project in 2002 and since this time an initial bulk-sampling programme
as well as a new drilling programme were undertaken to establish the viability of the project.
Overburden stripping began in February 2006, with the first gold produced in July 2006. Year to date
up to the end of May 2007, 27 705 tonnes of ore, averaging a recovered grade of 3.24g/t had been mined
on the Black Reef, from Black Reef Pits 1 and 2. All the ore is processed via a toll milling arrangement
at the Harmony Gold Ltd (“Harmony”) Randfontein Plant. Mining is conducted by contract miners,
namely Trollope Mining Services (Pty) Ltd (“Trollope Mining”). The conventional roll-over mining method
is employed on the mine, with rehabilitation an ongoing process. |
The Middelvlei Mine is located on the farm Middelvlei 225 IQ (“Middelvlei”), along the north-western
margin of the Witwatersrand Basin in the Randfontein area, 55km south-west of Johannesburg,
Gauteng Province, South Africa (Figure 2 and Figure 5). The mine is easily accessible via the N12
highway and R28 main road. The project is located at the following co-ordinates:
- Latitude 26º15’S; and
- Longitude 27º38’E.
At present, the two portions of Middelvlei, which have an approved old order mining licence (Re of Ptn 2
and Re of Ptn 3), are not subject to any formal agricultural, residential or commercial use. There is
evidence of old workings on the property, in the form of excavations, overburden dumps and slimes.
MGI also holds a new order Prospecting Right on Re of Ptn 6 and Re of Ptn 16 of Middelvlei.
A main railway line from Krugersdorp to Potchofstroom runs northeast to southwest across Re of Ptn 2
and 6, within 50m of the proposed mine site. Mining is not currently planned to the west of the railway
line on Re of Ptn 2.
Certain of the proposed opencast mining operations will be in the vicinity of the Middelvleispruit, which
flows north-south on the eastern edge of the mine site, approximately between Re of Ptn 2 and 3. A river
crossing will be constructed between Re of Ptn 2 and 3 to transport ore mined on Re of Ptn 3 to the main
mining area, when mining takes place on this portion.
There is no Eskom powerline on either Re of Ptn 2 or 3 and a generator is used as a power source for
lighting and water pumping. It is alleged that underground power cables were installed by Gold Fields
when they were conducting exploration on the property. Once current mining is fully underway, these
underground power cables can be utilised once again.
Drinking water is obtained from boreholes, as there are currently no potable water pipelines in the area.
Water for dust suppression is sourced from opencast pits where mining has been completed. |
The climate in the area is typical of the Highveld of South Africa, with mild winters and warm summers.
Temperatures rarely drop below zero degrees centigrade. The area falls within a summer rainfall area.
Mining operations can continue throughout the year.
The surface topography over the area is characterised by moderately undulating plains. Savannah
grassland is the natural vegetation in the area. The project occurs at an elevation of between 1,600m
above sea level (“amsl”) and 1,660m amsl. |
The property has been the focus of minor attention since 1929 when the first borehole was drilled on the
property. Initial exploration was conducted in order to asses the potential of the MVR and only an
underground mine was envisaged. Up to 1935, several trenches and winzes were excavated, but the
values were not considered encouraging at the time to warrant further work. In 1937, the VCR was
identified and sampled but the values also proved discouraging. Between 1945 and 1946, a drilling
programme (MV series) was carried out by Gold Fields between the outcrops and the northern boundary
of the Venterspost mine. These values also proved uneconomic at the time. After these disappointments,
interest in the area was abandoned, but was later revived because of a better understanding of the VCR,
in that it was found that VCR payshoots existed wherever Witwatersrand gold-bearing conglomerates
subcroped against the Ventersdorp lava.
A new drilling programme (M series) was initiated in 1969 by Gold Fields and was followed by 20 cross-cut
trenches in the outcrop area, which disclosed some high values on the VCR. It was concluded at the time
that the area might provide the company with a useful additional tonnage to be mined in the future. In
1995, further exploration was carried out on the VCR and Black Reef, which indicated that the project could
be exploited as an opencast operation. Gold Fields, however, never mined the gold deposit on Middelvlei.
During the last decade, studies have been conducted by Messer’s Muller, Moodly and Trevarthen, amongst
others. The property has been previously owned by, amongst others, Kloof Gold Mining Company Ltd
(“Kloof”) a subsidiary of Gold Fields, (Portion 2), and Gold Fields (Portion 3 and 6). MGI obtained the rights
to the property in 2002 and since that time have been exploring the mines economic potential. A detailed
review of the historical exploration that has taken place on the property is detailed in the following sections.
Mining has taken place on the Black Reef immediately to the north of the project boundary and VR and
VCR have been mined extensively immediately to the south of the project boundary.
|
|
Latest Annual Report
31 July 2008
Annual Report 2007 [PDF - 2.6MB]
Latest News
29 July 2008
Status of fundraising, release of Annual Financial Statements and notice of Annual general meeting
27 June 2008
Further cautionary announcement
12 May 2008
First Quarter Results and the opening of Ndlovu Shaft
|